Restroom
Site Locations - Cost Estimates
Precast Concrete Restrooms - CXT Inc.
Cortez Model - 2 Place Unisex
Basic Package* - "$30,758.89 "
"Freight to Pismo Beach FOB Spokane, WA - " "$1,844.67 "
Crane to off-load building - $890.00
Hook-up Utilities - $375.00
Total: "$33,868.56 "
Possible Add on Options:
Tile Floors - "$1,675.00"
Marine Package - "$3,456.00"
Stainless Steel Fixtures - "$1,879.00"
Skylights - $317.00
Other Roof and Wall Textures - "$1,633.00"
Montrose Model - 4 Place - Mens/Womens ( ships in two pieces)
Basic Package* - "$63,778.94 "
"Freight to Pismo Beach FOB Spokane, WA - " "$3,527.43 "
Crane to off-load building - "$1,483.96 "
Hook-up Utilities - $425.00
Total: "$69,215.33 "
Possible Add on Options:
Tile Floors - "$2,946.00"
Marine Package - "$3,849.00"
Stainless Steel Fixtures - "$2,828.00"
Skylights - $317.00
Other Roof and Wall Textures - "$1,840.00"
Options Available without pricing at this time
1. Stainless Steel Mirrors
2. Waste Paper Baskets
3. Exterior Sand Shower
4. Exterior Drinking Fountain
"* Basic Package - precast concrete flush toilet facility in an integral
earthtone color, barnwood textured"
"exterior wall and simulated cedar shake textured roof, as pictured in
the samples, with vitreous china "
"fixtures, pre-plumbed and pre-wired."
Precast Modular Restrooms Proposed Locations:
1. South Main St. Parking Lot - Modular
Facility located in existing Handicap parking space adjacent to Dolliver St.
2. Stimson Plaza - foot of Stimson Ave. at
the Boardwalk
3. Cypress St. - north of the stairway
to the beach opposite the Edgewater Hotel
4. Addie St. Parking Lot - at north side, at the foot
of Park Ave.
NOTE: Additonal Costs would include $10,000-$15,000 per site for Preparation for Installation
Constructed Restroom - Police Annex / Visitors Information Center
7 Place - Mens/Womens
"Cost Estimate = $65,000 (to be further refined upon receipt of working
drawings)"