Sidewalk Replacement Program - Phase Options

April 10, 2003

Sidewalk Replacement Program -Phase Options
All Prices are Calculated at Prevailing Wage

Add 300 Block of Pomeroy from Phase #2 to Phase #1
Moves 652 ln. ft. from Phase #2 and Adds to Phase #1

Additional Cost to Phase #1
STAMPED - COLORED CONCRETE
a. Cost Estimate - $82,839
i. Removal - $2.50 sq. ft x 7,172 sq. ft. = $17,930
ii. Curb and Gutter - 652 ln. ft. x $15.49/ln. ft. = $10,099
iii. Sidewalk - 5,542 sq. ft. x $9.89/sq. ft. = $54,810

Phase #1 - $216,805 + $82,839 = $299,644
Phase #2 - $238,125 - $82,839 = $155,286


 